SETTLEMENT · PIERS · LOAD TRANSFER

Underpinning changes where the house carries its load.

The important questions are not only which pier is used, but which foundation element it supports, where the load goes, how capacity is verified and whether stabilization or lift is the real objective.

Homeowner education · Reviewed November 2026
Do not wait for a web diagnosis

Rapid settlement, a failing support, utility strain or major structural distortion requires prompt qualified evaluation. Temporary shoring and repair design are not homeowner trial-and-error projects.

BEFORE PIERS

Confirm that settlement is the mechanism being repaired.

  • Map floor elevations and wall movement across the home.
  • Distinguish foundation settlement from slab settlement, wood movement or localized framing problems.
  • Review drainage changes, leaks, excavation, additions and prior repairs.
  • Identify foundation type, footing geometry and the actual load path.
  • Determine whether geotechnical information or subsurface exploration is needed.

SYSTEM TYPES

Different systems develop capacity differently.

  • Helical piers are rotated into soil and use helix geometry, installation torque and design correlations within the approved system.
  • Push piers are hydraulically advanced using the structure as reaction and require suitable structure, brackets and installation criteria.
  • Micropiles are small-diameter drilled and grouted elements used where loads, access or subsurface conditions call for a specialty foundation solution.
  • Traditional underpinning or enlarged footings may be appropriate in some conditions but require excavation sequence and structural design.

STABILIZE VS. LIFT

Do not let the word “repair” hide the objective.

Stabilization aims to limit further settlement by transferring load. Lifting attempts to recover elevation and can affect finishes, utilities, windows, doors and connected structures. The scope should state target movement, tolerances, risks and stop criteria.

INSTALLATION RECORD

The evidence is created while the work is happening.

  • Pier locations and the foundation element supported.
  • Design and proof/test loads where applicable.
  • Depth, extensions, torque or hydraulic readings for each element.
  • Bracket and connection details.
  • Lift sequence and before/after elevations if lift is attempted.
  • Concrete, grout, weld, corrosion-protection and inspection records as applicable.
  • As-built plan, permit closeout, warranty and future monitoring points.

COMPARE PROPOSALS

Price per pier is not a complete comparison.

Two proposals can use the same number of piers while supporting different walls, assuming different loads or using different capacity verification. Compare the engineering model, layout, installation criteria, exclusions, restoration and records—not only unit price.

SOURCE TRAIL

Technical references

These are starting references, not a project design. Product eligibility, code acceptance and installation conditions must be checked for the specific home.

REFERENCEICC Evaluation ServiceEvaluation Report Program

A guide to the evidence and conditions included in proprietary foundation-system evaluation reports.

REFERENCEICC Evaluation ServiceApproved acceptance criteria search

Includes the acceptance criteria used for helical pile systems and devices.

REFERENCEBuilding America Solution CenterPre-retrofit basement and crawlspace assessment

Places structural repair in the wider context of drainage, site and existing conditions.